The new building is back in full swing after the construction holiday. Because yes, construction has also come to a standstill in Romania in the summer.
The first floor will be poured next week (see photo). The next week the masonry work will start. The stones will be delivered this week. The formwork for the concrete pouring of the pillars for the 2 . will then also be startede floor.
The basic principle is still that the structural work will be completed before the end of this year. To be continued.